Since the switch has been turned for the first time in August 2013 starting up the mf60 commercial demonstrator at the premises of SMERAL in Brno the engineers performed endless test runs while improving and fixing numerous design and engineering details.
Simply put, they where doing exactly what a prototype is meant to be used for: trial, error detection and correction... Preparing a rock solid processing core for serial production that is ready for 24/7 hard core operation when it reaches a production site for installation. Most fixes required just from a couple of hours to a day or two. But eventually in early January 2014 careful review of collected test data resulted in the decision to proceed with a major redesign of the vapor off-take from the main reactor vessel, an effort which would interrupt test operations and scheduled demonstrations for several weeks.
SMERAL engineers did a great job in preparing and implementing the revised design in only 3 weeks. The almost finished result can be seen below:
The new design results in a significantly lower height, making the reactor more robust and energy efficient. Durability will be further improved by repositioning the microwave units for optimized cooling.
Once all measures are completed, a continuous test run for a minimum of 10 days is scheduled which will be monitored by an independent certification agency.
Simply put, they where doing exactly what a prototype is meant to be used for: trial, error detection and correction... Preparing a rock solid processing core for serial production that is ready for 24/7 hard core operation when it reaches a production site for installation. Most fixes required just from a couple of hours to a day or two. But eventually in early January 2014 careful review of collected test data resulted in the decision to proceed with a major redesign of the vapor off-take from the main reactor vessel, an effort which would interrupt test operations and scheduled demonstrations for several weeks.
SMERAL engineers did a great job in preparing and implementing the revised design in only 3 weeks. The almost finished result can be seen below:
redesigned mf60 reactor unit |
Once all measures are completed, a continuous test run for a minimum of 10 days is scheduled which will be monitored by an independent certification agency.